Additional Videos showing some of the individual processes that form part of the overall complex process of manufacturing concrete twin walls in our automated state of the art plant have been uploaded to our Youtube channel and are available within the Downloads section of the website. 

The last component of the main precast frame was installed in February 2017. Since then, follow-on trades including installation of Roof Steelwork, M&E, Blockwork and Stud Partitions, Stone and finishes have been ongoing. Oran Precast were re-contracted to provide a number of free-standing cantilever external walls and columns which form the perimeter walls and gated entrances for the Courthouse on the Mulgrave Street side and within the Secure Yard which abutts the nearby Limerick Prison Walls. 8m high 300mm thick walls were provided around the Secure Yard at the rear of the building.

Built to Specifications (Built2Spec), a four-year Horizon 2020 €5.5 million EU-funded project involving 20 European partners, seeks to reduce the gap between a building’s designed and as-built energy performance. To do this, the project will put a new set of breakthrough technological advances for self-inspection checks and quality assurance measures into the hands of construction professionals. This collection of smart tools will help building stakeholders at all levels in meeting EU energy efficiency targets, new build standards and related policy goals. The multi-million euro project shared among 20 European partners includes three from Ireland - NUI Galway, Oran Pre-Cast in Oranmore and Ecofix in Dublin.

Commenting on the project, Dr Magdalena Hajdukiewicz from NUI Galway, said: “The Built2Spec project and collaboration with companies such as Oran Pre-Cast allow our research to be applied to real buildings to tackle the problems of quality checks during the construction, as well as energy efficiency and indoor environmental conditions of operating buildings.”

For more information on IRUSE visit: www.iruse.ie and on Built2Spec visit:  https://built2spec-project.eu/

Further news regarding the collaboration between Oran Precast and NUIG can be viewed at http://www.nuigalway.ie/about-us/news-and-events/news-archive/2017/may2017/nui-galway-engineering-project-seeks-to-reduce-gap-in-energy-performance-of-buildings--1.html

 

Letterkenny Courthouse, one of four new build Courthouses to be built this year under the Courts Bundle PPP Project (Limerick, Wexford and Drogheda are the other three) is on schedule to open early in 2017. The last element of the precast frame was recently installed by Oran Precast on site. BAM Building are the main contractor and are contracted to design, build, finance and maintain the building for the next 25 years under a PPP model, the overall value of which is estimated to cost €135million.

The precast frame installation programme is on schedule. Aided by some benign weather this winter, and with two Oran Precast erection crews busy on site, Zone 2 (Main Courtrooms, 3&4 above) was completed ahead of the Christmas break. 40% of Zone 3 has beem completed at this stage also. Due to Site constraints, a mobile crane had to be located directly on the Ground Bearing Raft slab within the Building Zone 3 area. This meant that costly Road Closures could be avoided when installing some of the heavier elements at Roof level in Courtrrom 1 (see Top Left photo).

The 7,350 sqm building which will house District, Circuit, and Central Criminal Court sittings under one roof in a state-of-the-art Complex is progressing well on site. Oran Precast Ltd who were appointed to design, supply and install the large complex precast frame are using their full range of precast products in this project – Columns, Beams, Solid Walls, TwinWall, Lattice Slab, Hollowcore Slabs, Stairs, Landings. This large and complicated project with numerous floor level changes, double height courtrooms, non-stacking walls etc. is a good example of what can be achieved with precast construction.

The first of the 1st Floor Courtroom 6 Perimeter Walls were installed yesterday at the BAM - Limerick Courthouse job. Oran Precast are providing the full suite of precast products for this large and complex frame which incorporates numerous floor level changes, especially at 1st floor where the public courtrooms are located. There are 6 Courtrooms in total, serviced by 10 different Staircores. Wilson Architects and Malachy Walsh and Partners make up the main Design Team members, with Mercury Engineering looking after the M&E element of the contract. The project is intended to be fully BIM compliant.

Due to continued growth, Oran PreCast is expanding it's workforce again and a number of new positions have become available.

Please see our Careers Section for further details.

Some of the positions will be based in our new subsidiary Design Office in Birr, Co. Offaly which is due to open shortly.

Oran Precast continues to be heavily involved in the ambitious Research Project ‘Built2Spec’, which is funded under the EU Horizon 2020 Research and Innovation Programme and involves a team of Private companies, University bodies and Institutes from across Europe.

The project aims to develop new Quality Assurance tools in the area of Construction so that Retrofit and New Build projects in the near future can be managed and verified with a view toward meeting ambitious EU energy efficiency targets. These tools will use new technological advances in the area of 3D & Imagery, Building Information Modelling (BIM), Smart Building components, Energy Efficiency testing, Indoor Air Quality testing, Airtightness, Thermal and Acoustic testing.

In July 2015, a Built2Spec Project Meeting took place in Galway, hosted by the NUIG research team. A site visit to Oran Precast’s Office and manufacturing facility was one of the highlights of this meeting. Further information is available on the project website www.built2spec-project.eu.

 

Oran PreCast is expanding it's workforce and a number of positions have become available.

Please see our Careers Section for further details.

Some of the positions will be based in our new subsidiary Design Office, which is to be located in Birr, Co. Offaly.